Southern Africa: South Africa, Lesotho Water Project - Phase II By 2023

Photo: http://www.lhwp.org.ls/
Mohale Dam, Lesotho.

The Lesotho Highlands Development Authority expects the R11.2-billion second phase of the Lesotho Highlands Water Project to be completed by 2023, the project's executive manager, Mark Matchett, announced on Monday.

The massive joint project between South Africa and land-locked Lesotho will generate hydro-electric power for Lesotho while increasing the volume of water transferred to South Africa from the current 10-billion to about 15-billion cubic metres a year.

The first phase of the project - comprising a series of dams, hydropower stations and tunnels between South Africa and mountainous, landlocked Lesotho - was funded by the World Bank and completed in 2004.

The second phase will involve building the Polihali Dam in the Mokhotlong district, which is located in the northeastern part of Lesotho and, according to Wikipedia, includes both the highest terrain in the Maloti mountain range and the source of the Senqu River, Lesotho's primary watershed.

A new tunnel will also be built from from Polihali Dam to Katse Dam, along with new hydropower features and other advanced infrastructure.

Speaking at a briefing session in Johannesburg, Matchett said: "We are about to embark on a procurement process. This will run for a fairly intensive six- to nine-month period, and during this time we hope to have procured most of the design contracts. Towards the middle to the end of next year, we hope to be in a position to start procuring contracts for the construction works."

He said design work on the dam and tunnel was expected to start during the first or second quarter of next year, while construction was expected to commence during the third or fourth quarter.

Matchett said the new dam could reach its minimum operating level by 2022, if there were sufficient rain, and "if all goes well ... we are looking at completion by the year 2023."

Work on environmental studies, mitigation plans, resettlements and compensations had already begun and should be complete by the end of October or November.

Matchett said 2 500 workers were expected in the area at the height of the project. A township would be established and an existing lodge developed to meet the accommodation demand.

Tente Tente, the divisional manager of the project, said a policy was in place to ensure that proper procedures were followed by companies bidding for the tenders.

 - SAnews.gov.za and SAinfo reporter

Ads by Google

Copyright © 2014 SouthAfrica.info. All rights reserved. Distributed by AllAfrica Global Media (allAfrica.com). To contact the copyright holder directly for corrections — or for permission to republish or make other authorized use of this material, click here.

AllAfrica publishes around 2,000 reports a day from more than 130 news organizations and over 200 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.