Congo-Kinshasa: Inga Dam Mirage Recedes, Again

analysis

The latest projections for the Inga 3 hydroelectric project on the Congo River to become operational, cited in press reports last week, are 2024 or 2025. But even if the project is financed and constructed, says a new report, the project will likely provide only minimal electric power for the people of Democratic Republic of the Congo and burden the country with more unsustainable debt.

According to the report, "The project will sell most of its electricity to South Africa and to mines in eastern DRC. The report finds that losses along what would be the world's longest transmission line to South Africa could leave very little power available to the mines, and the Congolese people would receive little benefit in increased electricity. Under the most likely scenario, 88% of the power would be sold to South Africa, leaving just 90 MW for Kinshasa, rather than the 1000 MW claimed. Under the worst-case scenario, no power at all would be available for sale to consumers in Kinshasa."

...

AllAfrica publishes around 500 reports a day from more than 100 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.