The latest projections for the Inga 3 hydroelectric project on the Congo River to become operational, cited in press reports last week, are 2024 or 2025. But even if the project is financed and constructed, says a new report, the project will likely provide only minimal electric power for the people of Democratic Republic of the Congo and burden the country with more unsustainable debt.
According to the report, "The project will sell most of its electricity to South Africa and to mines in eastern DRC. The report finds that losses along what would be the world's longest transmission line to South Africa could leave very little power available to the mines, and the Congolese people would receive little benefit in increased electricity. Under the most likely scenario, 88% of the power would be sold to South Africa, leaving just 90 MW for Kinshasa, rather than the 1000 MW claimed. Under the worst-case scenario, no power at all would be available for sale to consumers in Kinshasa."
...