Ghana: Tema-Akosombo Road to Be Completed in 30 Months

18 August 2022

The 64km Tema-Akosombo Road is scheduled to be completed in 30 months.

The first project 6km of the road will be a dual carriageway with service lanes from the Ashaiman roundabout to Gbetsile while the next 7km from Gbetsile will be a three-lane dual carriageway, after which a two-lane dual carriage to Kpone will be created without service lanes.

The Minister of Roads and Highways, Kwasi Amoako-Attah, announced this on Wednesday when he embarked on a site inspection on the Tema-Akosombo Road.

He said the 11km Kpone to Atimpoku session of the road will be a single carriageway however, it would have an interchange at Asutsuare and a flyover at the Ashaiman roundabout.

The Minister added that there would be three river bridges and eleven footbridges on the entire stretch as well as walkways, streetlights and drainage systems to ensure safety on the road.

The project is being undertaken by Inzag Germany GMBH.

AllAfrica publishes around 400 reports a day from more than 100 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.