8 December 2017

Uganda: Compensation to Delay Karuma Power Project

Kiryandongo — Difficulties in acquiring land for the Karuma interconnection project is likely to delay the commissioning of the 600MW hydropower plant, the Uganda Electricity Generation Company Ltd chief executive officer, Mr Harrison Mutikanga, has said.

The power plant, whose construction commenced in August 2013, is expected to be commissioned in December 2018.

Mr Mutikanga said despite the progress of ongoing works at Karuma Hydropower project hitting 71 per cent, commissioning it on schedule remains uncertain due to land-related issues where transmission lines will cross.

Electricity from the power plant is expected to be evacuated through Karuma -Kawanda (305km), Karuma-Olwiyo (60km) and Karuma- Lira (80km). More than 4,000 affected people on the transmission routes will be compensated.

Mr Mutikanga said they are working closely with the ministry of Energy, Finance ministry and Uganda Electricity Transmission Co Ltd (UETCL) to ensure that the problems are rectified and the project is commissioned on schedule.

Mr Mutikanga, who was accompanied by other UEGCL board officials, was addressing the media on the project progress at Karuma on Wednesday during a site visit.

Mr Edward Mutesa, the principal project officer- social Aspect at UETCL, the firm undertaking the interconnection project, told Daily Monitor in an interview on Thursday that they are already behind schedule by six months due to emerging land disputes.

He noted that the biggest challenges have been experienced on the Karuma-Kawanda, the longest route where they encountered several overlapping tittles by landowners between the Nakasongola and Wakiso districts.

According to Mr Mutesa, owners of land on the Karuma-Lira route are being influenced by lawyers to get more money.

He said out of the 4,135 people affected by the interconnection project, 2,791 have so far been compensated Shs30b of the Shs56b meant to compensate all the affected land owners.

Mr Albert Byaruhanga, the Karuma Hydropower project manager, noted concerns on the dam section and its power intake as well as underground caverns and tunnels.

"This project is designed to serve more than 50 years, in the long run, we worry that it can create a lot more problems in future during the operation of the plant if quality control is not maintained," Mr Byaruhanga said.

Uganda

Bobi Wine - My Plan On Landing in Uganda

Ugandan pop star-cum-politician Bobi Wine says he is set to return to Kampala after his medical tour of the US. Read more »

See What Everyone is Watching

Copyright © 2017 The Monitor. All rights reserved. Distributed by AllAfrica Global Media (allAfrica.com). To contact the copyright holder directly for corrections — or for permission to republish or make other authorized use of this material, click here.

AllAfrica publishes around 600 reports a day from more than 140 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.