Ethiopia: Power Agency Lights up Gonder With 246 Million Br

Ethiopian Electric Power has upgraded and expanded a distribution station located in Gonder for 246 million Br.

The project took one year to complete, and it has begun operation with full capacity last month, according to Dawit G.Egziabher, the project site manager.

The expansion project upgraded the station's distribution capacity from 40MW to 166MW and installed two new transformers that can carry 15,000 volts of electricity.

These upgrades have relieved the power interruptions that were cause for a lot of complaints from the four industrial parks in Azezo, according to Dawit.

In addition to Gonder, the upgrade will also benefit its neighbouring towns

See What Everyone is Watching

More From: Addis Fortune

Don't Miss

AllAfrica publishes around 600 reports a day from more than 150 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.