Namibia: Depleted Stocks At Skopiorn Zinc Refinery Result in Temporary Closure

Skorpion Zinc on Friday in a statement confirmed the temporary closure of its refinery for a period of five weeks.

This follows the depletion of ore stocks as a result of an unprotected strike from 22 February until 6 March by employees of mining contractor, Basil Read.

According to the statement, the company said every effort is being made to mitigate impacts on customers, on the business as a whole and on employees.

"Maintenance that was planned for later this year will be undertaken during this time period. Skorpion Zinc is working to optimise the FY19/20 business plan so as to minimise the impact over the remainder of the life of the Pit112 project," said Skorpion ZincCorporate Affairs and Sustainability Manager, Nora Ndopu.

Earlier this week, Skorpion Zinc General Manager Irvinne Simmata had warned that sthe strike in itself could result in the restructure and/or premature closure of the operations.

Work stoppages such as these have an enormously negative impact on the business, Simmata said.

This has been the third disruption in the past seven months and Simmata said the business is set to loss around N$314 million.

Skorpion came into production in 2003, and was acquired from Anglo American by Vedanta Zinc International in 2010/2011.

See What Everyone is Watching

More From: Namibia Economist

Don't Miss

AllAfrica publishes around 600 reports a day from more than 150 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.