Julius Berger (JB) Plc., the company reconstructing the Lagos-Sagamu interchange axis of the Lagos-Ibadan expressway, has disclosed that it would close the two Lagos-bound lanes of the Kara (Ogun River) bridge for four months, spending two months on each lane, to enable it reconstruct the 600 metres stretch of the road between the Lagos-end of the bridge and Ojodu Berger.
The firm said it would take two months, beginning from next Saturday, to rehabilitate the Lagos-bound stretch of the 600 metres, and that once that is done, it would move to the Sagamu-bound lane for another two months, adding that work on the stretch would be completed on October 31.
...