Kenya: Japan Still Hopeful About Thiba Dam

10 December 2019

The Japanese government has expressed concerns over delayed resumption of the stalled Sh20 billion Thiba Dam project meant to increase rice production in the giant Mwea Irrigation Scheme in Kirinyaga County.

Japan's Ambassador to Kenya, Horie Ryoichi, blamed the delays on a difference of opinion between stakeholders and land issues.

"It is true the project is delaying a little bit but I believe the problems affecting its construction will be resolved," he told journalists as he toured the multi-million private Nice Rice Millers in Ngurubani town which is owned by local entrepreneur Njiru Mkombozi.

He exuded confidence that Kenya will ensure faster completion of the mega project which is being funded by Japan.

FINANCES

Construction of the dam stalled this year due to financial constraints that led to the contractor Strabag International sending its workers home.

A pay dispute between the firm and Treasury is at the centre of delays after the government failed to release money to the company.

Financial hiccups were further complicated by land issues after some of locals who had surrendered their land for construction walked back on their decision and threatened repossession.

The project, which was supposed to be completed in 45 months, was commissioned by President Uhuru Kenyatta in 2017.

Local leaders have previously warned that if the current situation is not resolved, the project risks going the Kimwarer Dam way.

ASSURANCES

Once completed, rice production was projected to double from 80,000 tonnes at the time to 160,000 tonnes a year.

Recently, Water and Irrigation Principal Secretary Joseph Irungu also assured rice farmers from the region that construction would go on.

Speaking at Rukenya village after touring the dam, he admitted that the project halted in October due to non-payment of the contractor.

He explained that Treasury had agreed to pay Strabag International while asking farmers and local leaders to be patient.

"The money to pay the contractor will be factored into the Supplementary Budget and there should be no cause for alarm," he stated.

Mr Irungu said the contractor is expected to recall workers and resume construction soon.

See What Everyone is Watching

More From: Nation

Don't Miss

AllAfrica publishes around 600 reports a day from more than 140 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.