A new modest 50MW private thermal power plant has been completed in Hwange and is expected to start feeding the power into the national grid before year end.
Also under construction in the same district is a solar power plant which is ready to go online, pushing 5MW into the grid, within a fortnight. The construction of the small power station by Zimbabwe Zhongxin Electrical Energy (ZZEE), situated about 10km west of Hwange town is now 100 percent complete with work on the substation 99 percent complete. The company is now waiting for the arrival of isolator equipment, which is set to be dispatched from China in the next few weeks.
...