Uganda: East African Crude Oil Pipeline Project Secures Massive Financial Injection From African Banks

Kampala, Uganda — EACOP, the company in charge of the construction and future operation of the East African Crude Oil Pipeline project from Kabaale in Uganda to Tanga in Tanzania, has got a massive financial boost from several top African banks. In a statement, EACOP said the injection of cash "also demonstrates the support of financial institutions on this transformative regional infrastructure."

The East African Crude Oil Pipeline Ltd today announced that it has closed the first tranche of external financing for the project, provided by a syndicate of financial institutions including regional banks such as African Export Import Bank (Afreximbank), The Standard Bank of South Africa Limited, Stanbic Bank Uganda Limited, KCB Bank Uganda and The Islamic Corporation for the Development of the Private Sector (ICD).

"The successful closing of this first tranche of external financing represents a significant milestone for EACOP and its shareholders TotalEnergies (62%), Uganda National Oil Company Limited (UNOC - 15%), Tanzania Petroleum Development Corporation (TPDC - 15%) and CNOOC (8%)," EACOP stated.

Tranches are segments or slices of a pooled collection of financial instruments, such as loans or mortgages, that are structured to divide risk or investment return among different investors.

In Uganda and Tanzania, the construction of the EACOP pipeline is progressing well with a continued focus on safety, environmental sustainability, and local community engagement. The overall project progress exceeded 50% end 2024. More than 8,000 Ugandan and Tanzanian citizens are employed on the project, about 400,000 manhours of training have been provided so far and 500 M$ spent locally on goods and services.

The East African Crude Oil Pipeline is a crude oil export infrastructure that will transport Uganda's crude oil from Kabaale - Hoima in Uganda to the Chongoleani peninsula near Tanga in Tanzania for export to the international market.

Upon completion, it will have the capacity to transport 246,000 barrels of crude oil per day. This major export system includes 1,443 km (296 km in Uganda and 1,147 km in Tanzania) of insulated and buried 24-inch pipeline, 6 pumping stations, two pressure reduction stations and a marine export terminal in Tanzania (with a 3 MWp solar plant), all along connected to national primarily hydro- based grids for power supply.

"The project is committed to the highest Environment and Social standards such as those of the International Finance Corporation and the Equator Principles," an official said.

AllAfrica publishes around 500 reports a day from more than 110 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.