Southern Africa: Namibia's Road Network Faces Crisis As Half Exceed Lifespan

Half of Namibia's roads have exceeded their intended lifespan, the Roads Authority (RA) has reported.

Recent rains have further weakened the road network, leading to closures and detours in various regions.

The collapse of the Aris River Bridge on the B1 between Windhoek and Rehoboth in March prompted the construction of a temporary bypass costing N$2.9 million, RA spokesperson Hileni Fillemon confirmed on Monday.

This single-lane bypass, built on the night of 20 March, includes a four-barrel 1.2-metre culvert and operates on a stop-and-go basis, Fillemon stated.

She said traffic will remain on the bypass for three weeks before being shifted to a completed two-lane permanent bypass.

Fillemon noted that permanent repairs to the bridge will not commence until investigations are completed.

"Geotechnical investigations need to be undertaken to determine the foundation conditions for the new bridge structure," she added, noting that the estimated time for design and construction is seven months.

A final project budget will only be determined once the bridge design is completed.

Fillemon further stated that the Swartz Bridge near Osona Village, located on the old B1 between Windhoek and Okahandja, has been closed due to signs of settlement on one of its piers. It was closed as a precautionary measure, and a contractor has been appointed to begin rehabilitation, though the timeline for reopening remains unknown.

She stated that the nearby Osona Base Bridge on the new dual carriageway has not sustained any damage.

She also noted that flooding has compromised multiple national and regional roads, and confirmed that the MR76 road from Uis to Kamanjab is impassable in several sections due to river crossings filled with mud and sand, potholes, and damaged culverts. The section from Khorixas to Uis has experienced significant washaways and a loss of road quality.

The D2612 road between Sorris-Sorris and Twyfelfontein has also suffered structural damage, including gravel loss and sand accumulation, making the route hazardous, with no alternative available.

The M126 from Khorixas to Bergsig and Palmwag to Kamanjab, according to Fillemon, is washed out and flooded.

Other roads affected include MR128 (Palmwag to Sesfontein), C35, C14 and C39, many of which are impassable due to erosion, debris or flooding.

The Ovitoto Road via Windhoek, Kappsfarm and Midgard is also closed following damage to a concrete drift at Midgard River.

Repairs will be carried out once riverbed conditions allow, and an alternative route is available via Okahandja and Von Bach Dam, she said.

To address the situation, RA has deployed contractors to affected areas.

"We have deployed contractors in various regions to make repairs whenever possible since we continue to receive good rainfall," she said.

The authority also stated that it is working to reduce long-term weather-related vulnerabilities by exploring different road construction materials. However, it emphasised that a lack of funding remains a major challenge.

"Providing an adequate budget to the RA is crucial to enable us to preserve our roads and avoid further deterioration," she added.

AllAfrica publishes around 500 reports a day from more than 110 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.