Namibia: Health Ministry Commits N$1.8 Million Towards Rupara Maternity Ward Construction

The Ministry of Health and Social Services has committed N$1.8 million to complete the Rupara Maternity Ward project.

This commitment was confirmed during a meeting with stakeholders, including the Development Bank of Namibia (DBN) and the Kavango West Regional Council, at the Rupara Health Centre on Friday.

The funds are intended to cover the remaining 40% of construction work required to finalise the healthcare facility.

The project, which commenced three years ago, is currently 40% completed following procurement process delays.

Follow us on WhatsApp | LinkedIn for the latest headlines

Health ministry programme officer and infrastructure planner Boniface Hamutenya said the outstanding work includes electrical, plumbing, and external infrastructure.

"The health ministry has pledged N$1.8 million to complete the remaining work, with procurement processes currently underway," said Hamutenya.

He noted that the project team expects to have a more definitive completion date following the health ministry's procurement meeting next week, and expressed his hopes of finally delivering this critical healthcare facility to the local community.

"Our ministry's financial commitment is expected to help expedite the project's completion and address the community's urgent healthcare infrastructure needs," said Hamutenya.

DBN, which initially funded the project with N$1 million, expressed growing concern about the lack of progress.

DBN's executive for marketing and corporate communications, Jerome Mutumba, emphasised the need for a clear timeline and commitment from all parties, citing reputational risks and the bank's public accountability.

"This project was scheduled to be handed over in April last year, but the project has experienced delays due to unforeseen circumstances. The purpose of this meeting is to address those challenges and to know what is required from us, because this is beginning to become more of a reputational risk for the bank having an incomplete project which has a DBN signature on it, and we are not able to account for what is happening," said Mutumba.

Kavango West governor Verna Sinimbo acknowledged the frustrations but highlighted the challenges associated with central government procurement processes.

"These delays are making life difficult for our communities who desperately need this healthcare infrastructure," she said.

AllAfrica publishes around 500 reports a day from more than 80 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.