No Power Outages - South African Power Utility

Power utility Eskom has assured South African that there will be no load-shedding as a result of delays in the completion of the country's new coal-fired power plant.
  • South Africa:   No Outages Because of Medupi - Eskom

    SA Info, 11 July 2013

    There will be no load-shedding as a result of delays in the completion of South Africa's new Medupi coal-fired power plant, says state company Eskom. Read more »

  • South Africa:   Consultants to Get Medupi On Track

    SA Info, 11 July 2013

    South African Public Enterprises Minister Malusi Gigaba, saying he was "extremely disturbed" by further delays to the completion of Eskom's Medupi coal-fired power station, has… Read more »

  • South Africa:   Delay in Medupi Unit 6

    Govt of SA, 8 July 2013

    The Minister of Public Enterprises Malusi Gigaba has noted Eskom's announcement about Medupi's delay to deliver first power in December 2013 as originally planned. Read more »

Video

  • 9 July 2013
    Energy Woes For South Africa
    Author:
    enewschannel
    Publisher:
    enewschannel
    Publication Date:

    Economist Richard Downing says the delay on the Medupi Power Plant does not come as a surprise considering all the strikes that have happened at the ... see more »

  • South Africa:   The Medupi Delay - Why You Should Care

    Daily Maverick, 9 July 2013

    On Monday Eskom announced, as many had already predicted, that the Medupi Power Station would not be operational at the end of this year. There is, however, much more at stake than… Read more »

  • South Africa:   Third Medupi Delay - Will Heads Roll?

    DA, 8 July 2013

    The announcement today by Eskom that the Medupi power station will not meet its December 2013 deadline and that first power from Medupi could only be expected in the second half of… Read more »

  • South Africa:   SA Extends New Power Plant Deadline

    SA Info, 8 July 2013

    South Africa's new Medupi coal-fired power station, under construction in Limpopo province, is unlikely to deliver its first power to the country's grid by the end of this year as… Read more »

  • South Africa:   Medupi Promises Require Enforcement Plan

    DA, 12 April 2013

    Minister of Public Enterprises, Malusi Gigaba, is adamant that the December 2013 deadline for the Medupi power plant to start producing power will be met. However, he has not put… Read more »

InFocus

Follow AllAfrica

AllAfrica publishes around 400 reports a day from more than 100 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.