Nigeria: Probe of Zungeru Power Plant Is Aimed At Ensuring Due Process, Says Lawan

13 December 2022

The President of the Senate, Ahmad Lawan, has said that the Senate decided to organise an investigative hearing on the ongoing bid on a concession of the Zungeru Hydroelectric Power Plant (ZHPP) located in Niger State, to ensure due process in the exercise.

The investigative hearing, which held on Tuesday, was organised by the Senate Committee on Power in line with the resolution adopted by the Senate at its plenary sitting of Wednesday, 23rd November, 2022.

Lawan explained that the thrust of the motion, sponsored by the chairman of the committee, Senator Gabriel Suswan, was to request the Senate to invoke its oversight constitutional responsibility to avert the transfer of unresolved liabilities and future third-party claims to government.

He said the probe would ensure that the proposed concession of the Zungeru Hydroelectric Power Plant (ZHPP) was conducted on a 'value for money criteria' bearing in mind the huge external loans and annual budgetary releases expended on its construction.

He said: "I am glad to note that the committee has extended invitation to all concerned stakeholders to come forward with their inputs, observations and contributions to the work of the committee in carrying out its mandate.

"The concerns of the Senate, which culminated into this investigative hearing must be seen by all well-meaning Nigerians from the context of government's recent experience with the privatization of power assets in Nigeria which has continued to attract public outcry and criticism.

"It is noteworthy that while a segment of the public has applauded the modest gains of the privatization of government-owned power assets in Nigeria, mounting challenges that emerged after the exercise have made many to question the credibility of the process that produced the successor companies and the viability of such companies, hence the need for extreme caution in the concession of the remaining government-owned power assets including the ZHPP.

"The precarious condition of the Nigerian power sector is indeed puzzling considering relentless investments and special interventions made by successive administrations to change the fortunes of the sector for the better.

"Available data indicates that between 2015 and 2022 alone, the Nigerian national grid collapsed 98 times.

"This immediately brings to question whether the power to be generated from the ZHPP upon commencement of operation will be successfully and fully evacuated and if not, what will be the implication on the capacity of the concessionaire to meet its obligations under the Concession Agreement being contemplated.

"Failure to address such issues in the past have put government in an unenviable position where billions of naira are currently being paid to service contractual obligations that should have been avoided by government if proper due diligence and consultation was done by relevant MDAs.

"It is therefore, expected that in the course of this investigative hearing, concerned stakeholders invited by the committee will take advantage of this avenue to answer the above posers and many more as may be directed at them by the chairman and members of the committee towards reaching informed recommendations that will form the final decision of the Senate at plenary regarding the bid to concession the ZHPP.

"Before I conclude, I wish to state here that while the Senate recognizes the respective statutory roles of the Infrastructure Concession Regulatory Commission (ICRC), the National Council on Privatization and its secretariat, the Bureau of Public Enterprises (BPE) and other MDAs involved in the proposed concession of the ZHPP, the Senate has a higher constitutional responsibility to carry out this investigative hearing to expose any semblance of corruption, inefficiency and waste as envisaged by sections 88 and 89 of the 1999 Constitution.

"You must therefore, take this investigative hearing seriously as its outcome would determine the final position of the Senate on the proposed concession of the ZHPP," Lawan said.

The chairman of the committee, Suswan, said the hearing afforded key players in the proposed concession on the ZHPP the opportunity to shed light on the many questions that have trailed the concession process since it was made public.

AllAfrica publishes around 500 reports a day from more than 100 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.