Liberia: Western Cluster's Road Permit Suspended

Liberia's Public Works Ministry has suspended the road user permit (RUP- 220620-004) issued to Western Cluster Limited (WCL) for "violation of the terms of the permit."

The Ministry announced the decision Wednesday, 8 May 2024, days after President Joseph Nyumah Boakai ordered the company's closure for extracting the nation's resources, damaging the roads, and leaving no benefits for the people.

The Public Works Ministry said the RUP gave Western Cluster the right to commercially haul iron ore on the Freeport of Monrovia-Bomi Hills Road corridor.

In the notice sent to the company through its country representative, the Ministry noted specifically that "WCL persistently violated Section II (d)(e) of the permit.

The Ministry accuses WCL of employing trucks longer than the permitted 34 feet in length and 8.5 feet in weight and carrying an axle load of about 40 tons--far beyond the allowable 30 tons.

The ministry further stated that it observed and documented Western Cluster's trucking of iron ore throughout the day and night, contrary to the limitation stipulated in the permit.

[bsa_pro_ad_space id=1]

It explained that the permit restricts the trucking of iron ore only between 7 pm to 6 am.

The Ministry of Public Works further charged Western Cluster for non-compliance with Section III (a) of the permit, which requires the company to erect and install weighbridges at the point of departure and Klay junction, respectively.

The ministry claims the company has failed to uphold this key transparency and accountability measure.

Moreover, the ministry niched Western Cluster to its glaring failure to maintain and repair the referenced road corridor, thereby eroding pliability and posing challenges to other road users.

The works ministry, however, recalls that before the issuance of this notice suspending Western Cluster's road user permit, a November 6, 2023 suspension was effected against these very violations.

"What is even more frustrating is that the Ministry of Public Works on November 6, 2023, suspended the permit for similar violations, which suspension was lifted after WCL assured the ministry of curing these violations within the soonest possible time," the release said.

The Ministry concluded that it had no option but to decide against WCL 's lack of good faith in fulfilling its obligations until any/all violations and defaults under this permit are cured.

It cautioned that the company risks terminating its road user permit if Western Cluster fails to cure these stipulated violations within 60 days.

AllAfrica publishes around 600 reports a day from more than 110 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.