Nigeria: TCN to Re-Erect Three Towers Along Kainji-Birnin Kebbi Line

20 May 2025

Abuja — The Transmission Company of Nigeria (TCN) has announced that work was ongoing to re-erect three towers that collapsed along the 330kV Kainji-Birnin Kebbi transmission line earlier in May, caused by a heavy wind that felled the towers.

TCN said it has mobilised three separate contractors to the site, each assigned to handle the reconstruction of one tower, noting that the 'strategic deployment' aims to accelerate the restoration process and minimize downtime on the line.

"In the meantime, efforts have been made to cushion the impact of the disruption in bulk power supply to Kaduna Distribution Company (Disco), which affects some of its customers.

" Sokoto and Birnin Kebbi are currently receiving between 6 MW and 7 MW of bulk electricity from the Mando Transmission substation via the 132kV Mando-Zaria-Funtua-Gusau-Talata Mafara-Sokoto-Birnin Kebbi line," a statement from the organisation said.

TCN appreciated the patience and understanding of the affected communities as contractors work assiduously with the supervising engineers to rebuild the towers and restring the 330kV transmission line.

"We regret the inconvenience caused by the tower collapse and are committed to restoring full supply as quickly as possible," it said.

AllAfrica publishes around 500 reports a day from more than 90 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.