Impending Djibouti Action To Denounce Rule Of Law A Warning To Business Investors

31 July 2019
Content from a Premium Partner
InfoWire

Application to have high court in Djibouti rule international adjudications null and void contravenes global legal system and threatens investment

Government of Dubai Media Office – 29 July, 2019: A decision to be taken later this week by the government of Djibouti to apply to the country's high court to rule all previous international adjudications null and void is a complete disregard for and contravention of the global legal system and existing contracts.

The move is proof of Djibouti's complete disregard for recognized legal practice and respect for contracts calling into question any investment in the country both now and in the future.

Doraleh Container Terminal SA (DCT), a Djibouti port operator owned 33.34% by DP World Group, and 66.66% by Port de Djibouti S.A., an entity of the Republic of Djibouti, has been successful in five previous substantial rulings over the last three years by the London Court for International Arbitration in London and the High Court of England and Wales. All have been ignored by Djibouti despite the original contract for the concession being written under English law.

The most recent decision by an LCIA Tribunal on 29 March this year found that by developing new container port opportunities with China Merchants Port Holdings Co Limited (China Merchants), a Hong-Kong based port operator, Djibouti has breached DCT's rights under its 2006 Concession Agreement to develop a container terminal at Doraleh, in Djibouti, specifically, its exclusivity over all container handling facilities in the territory of Djibouti.

The Tribunal ordered Djibouti to pay DCT $385.7 million plus interest for breach of DCT's exclusivity by development of container facilities at Doraleh Multipurpose Terminal, with further damages possible if Djibouti develops a planned Doraleh International Container Terminal (DICT) with any other operator without the consent of DP World.

The Tribunal also ordered Djibouti to pay DCT $88 million for historic non-payment of royalties for container traffic not transferred to DCT once it became operational. Djibouti is also ordered to pay DCT's legal costs.
The Tribunal's Award recognises that the 2006 Concession Agreement remains valid and binding, as has also been confirmed by another LCIA Tribunal and the English courts.  DCT and DP World continue to seek to uphold their legal rights in a number of legal fora, following Djibouti's unlawful efforts to expel DP World from Djibouti and transfer the port operation to Chinese interests.

Litigation against China Merchants also continues before the Hong Kong courts. DP World has previously issued public notices, following the confirmation of the validity of the 2006 Concession Agreement in a judgment in 2018, warning others against interfering with its and DCT's concession rights.

AllAfrica publishes around 400 reports a day from more than 100 news organizations and over 500 other institutions and individuals, representing a diversity of positions on every topic. We publish news and views ranging from vigorous opponents of governments to government publications and spokespersons. Publishers named above each report are responsible for their own content, which AllAfrica does not have the legal right to edit or correct.

Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica. To address comments or complaints, please Contact us.